Year                             Project

Tullow Oil     
                     

2011                           2 well pads and 10Km access Road.
2011                           Air Strip Improvement and 25km access Road.
2010                           preparation of Drill pads and access Roads.
2008                          Construction of 70km access road to drilling sites and Earth works.

Hima cement

2008                           Earth works for Rwenzori project.
2008                           Construction of Carpentry work shop.
2006                           Mining and Transportation of clay.
2005                           Construction of Social center.

Uganda-Ministry of Works

2010                           Kaiso Tonya Road 36 Km
2005-08                      Rehabilitation of 200km of Gravel Roads in Bundibugyo & Adjumani

Uganda –Ministry of Local Government

2010                         Masindi and Kasese Town Councils
2005-10                     Rehabilitation of 80 Km Road in Kasese District.
         Others    
           
2012                          CNOOC – Kanywataba Drill Pad, Wasa Bridge reconstruction      
           